Boeing Increases 787 Dreamliner Production Rate

Boeing last week rolled out the first 787 Dreamliner built at the new rate of five-airplanes-per-month. The airplane is the 83rd 787 to be ...

Boeing last week rolled out the first 787 Dreamliner built at the new rate of five-airplanes-per-month. The airplane is the 83rd 787 to be built.
Boeing earlier this year increased the rate from 2.5 to 3.5 airplanes per month and is on track to achieve a planned 10-per-month rate by late 2013. The program production rate accounts for airplanes built at Boeing South Carolina and Everett, including the Temporary Surge Line that was activated earlier this year in Everett.
As just one example illustrative of the efforts happening across the production system, a team developed a small piece of protective equipment to cover the electronic actuators that help move the horizontal stabilizer. The plastic covering is now used across the program to protect the actuators during the production process. In addition, this small change has resulted in quicker production completion times.
Among the new tools being deployed to improve productivity in the Final Assembly areas are Orbital Drilling machines. The machines are used to drill holes to attach the wings to the center fuselage section of the airplane. The drilling technique is unique in that the cutter rotates in a circular motion to carve out the hole, rather than a conventional drill that cuts straight into the material. Benefits of the machines include improved precision and time savings for mechanics. A third benefit is improved safety as the machines require lower thrust and torque.

To date, 35 787s have been delivered to eight airlines and the program has more than 800 unfilled orders with 58 customers worldwide.